Z66 - MARGUERITE AVENUE / SOUTH BEND AVENUE RECONSTRUCTION PROJECTR&G Construction Co. D&G Excavating, Inc. Kuechle Underground, Inc. DUININCK, INC. 
Item No.ItemUnitsQuantityUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal PriceUnit PriceTotal Price
2021.501MOBILIZATIONLS1$21,000.00$21,000.00$32,500.00$32,500.00$35,400.00$35,400.00$51,400.00$51,400.00
2101.507GRUBBINGEACH1$700.00$700.00$500.00$500.00$1,000.00$1,000.00$1,000.00$1,000.00
2104.501REMOVE CURB & GUTTERL F2,965$3.50$10,377.50$3.95$11,711.75$6.50$19,272.50$3.00$8,895.00
2104.503REMOVE CONCRETE SIDEWALKS F14,520$1.00$14,520.00$1.40$20,328.00$0.50$7,260.00$0.75$10,890.00
2104.505REMOVE CONCRETE PAVEMENTS Y479$6.00$2,874.00$6.00$2,874.00$9.50$4,550.50$13.50$6,466.50
2104.505REMOVE BITUMINOUS SURFACINGS Y5,490$2.00$10,980.00$1.50$8,235.00$3.25$17,842.50$2.50$13,725.00
2104.509REMOVE CATCH BASINEACH4$250.00$1,000.00$300.00$1,200.00$125.00$500.00$250.00$1,000.00
2104.509REMOVE MANHOLEEACH6$300.00$1,800.00$450.00$2,700.00$150.00$900.00$325.00$1,950.00
2104.513SAWING BIT PAVEMENT (FULL DEPTH)L F375$3.00$1,125.00$1.75$656.25$3.00$1,125.00$2.50$937.50
2105.501COMMON EXCAVATION (P)C Y2,550$11.00$28,050.00$5.75$14,662.50$4.50$11,475.00$16.00$40,800.00
2105.522SELECT GRANULAR BORROW (CV)C Y1,025$5.00$5,125.00$14.25$14,606.25$17.50$17,937.50$20.00$20,500.00
2105.526SELECT TOPSOIL BORROW (LV)CU YD350$15.00$5,250.00$25.00$8,750.00$14.00$4,900.00$32.00$11,200.00
2105.604GEOTEXTILE FABRIC TYPE VS Y5,985$1.80$10,773.00$1.75$10,473.75$2.50$14,962.50$1.35$8,079.75
2211.503AGGREGATE BASE (CV) CLASS 5 MODIFIED (P)C Y2,055$22.00$45,210.00$18.75$38,531.25$16.50$33,907.50$27.00$55,485.00
2360.501TYPE SP 12.5 WEARING COURSE MIX (3,C)TON1,285$88.70$113,979.50$88.70$113,979.50$90.00$115,650.00$88.70$113,979.50
2451.609AGGREGATE FOUNDATIONTON50$25.00$1,250.00$17.00$850.00$23.00$1,150.00$20.00$1,000.00
2502.5416" PERF PVC PIPE DRAINL F1,230$10.00$12,300.00$9.95$12,238.50$10.00$12,300.00$9.25$11,377.50
2503.5114" PVC PIPE SEWERL F1,075$25.00$26,875.00$18.00$19,350.00$12.00$12,900.00$27.50$29,562.50
2503.5118" PVC PIPE SEWERL F1,075$33.00$35,475.00$36.00$38,700.00$44.00$47,300.00$40.00$43,000.00
2503.602CONNECT TO EXISTING STORM SEWEREACH2$1,000.00$2,000.00$1,000.00$2,000.00$1,500.00$3,000.00$1,550.00$3,100.00
2503.602CONNECT TO EXISTING SANITARY SEWEREACH2$1,500.00$3,000.00$1,500.00$3,000.00$2,900.00$5,800.00$1,625.00$3,250.00
2503.6028"X4" PVC WYEEACH29$300.00$8,700.00$210.00$6,090.00$900.00$26,100.00$550.00$15,950.00
2503.60315" PIPE SEWERL F692$42.50$29,410.00$42.00$29,064.00$50.00$34,600.00$47.00$32,524.00
2504.6026" GATE VALVE & BOXEACH9$1,600.00$14,400.00$1,450.00$13,050.00$1,400.00$12,600.00$1,180.00$10,620.00
2504.602HYDRANTEACH4$3,500.00$14,000.00$3,600.00$14,400.00$4,000.00$16,000.00$3,200.00$12,800.00
2504.6026"X6" TEE FITTINGEACH6$750.00$4,500.00$650.00$3,900.00$600.00$3,600.00$550.00$3,300.00
2504.6026" PIPE BEND 45 DEGREEEACH2$400.00$800.00$550.00$1,100.00$190.00$380.00$400.00$800.00
2504.6021" WATER SERVICE (COMPLETE)EACH29$1,600.00$46,400.00$1,675.00$48,575.00$1,100.00$31,900.00$1,400.00$40,600.00
2504.6026" PIPE BEND 11.25 DEGREEEACH5$400.00$2,000.00$500.00$2,500.00$185.00$925.00$400.00$2,000.00
2504.6026" SLEEVEEACH4$400.00$1,600.00$500.00$2,000.00$1,200.00$4,800.00$1,250.00$5,000.00
2504.6036" PVC WATERMAINL F1,461$27.00$39,447.00$30.50$44,560.50$40.00$58,440.00$36.00$52,596.00
2506.501CONST DRAINAGE STRUCTURE DESIGN FL F9.8$360.00$3,528.00$275.00$2,695.00$350.00$3,430.00$365.00$3,577.00
2506.502CONST DRAINAGE STRUCTURE DESIGN AEACH3$3,000.00$9,000.00$2,475.00$7,425.00$1,900.00$5,700.00$2,200.00$6,600.00
2506.60348" DIA. SANITARY SEWER MANHOLELIN FT46.7$400.00$18,680.00$315.00$14,710.50$300.00$14,010.00$345.00$16,111.50
2521.5016" CONCRETE WALKS F3,205$4.65$14,903.25$5.25$16,826.25$4.60$14,743.00$4.85$15,544.25
2521.5014" CONCRETE WALKS F12,001$3.20$38,403.20$3.25$39,003.25$3.00$36,003.00$3.10$37,203.10
2531.501CONCRETE CURB & GUTTER DESIGN B618L F2,970$10.00$29,700.00$11.00$32,670.00$10.00$29,700.00$10.00$29,700.00
2531.5076" CONCRETE DRIVEWAY PAVEMENTS Y570$46.60$26,562.00$44.00$25,080.00$46.00$26,220.00$48.15$27,445.50
2531.6047" CONCRETE VALLEY GUTTERSQ YD141$59.00$8,319.00$60.00$8,460.00$60.00$8,460.00$59.00$8,319.00
2531.618TRUNCATED DOMESS F100$40.00$4,000.00$40.00$4,000.00$40.00$4,000.00$40.00$4,000.00
2563.601TRAFFIC CONTROLLS1$3,000.00$3,000.00$3,100.00$3,100.00$3,200.00$3,200.00$3,000.00$3,000.00
2573.530STORM DRAIN INLET PROTECTIONEACH5$100.00$500.00$195.00$975.00$200.00$1,000.00$150.00$750.00
2573.602TEMPORARY ROCK CONSTRUCTION ENTRANCEEACH4$750.00$3,000.00$1,500.00$6,000.00$680.00$2,720.00$500.00$2,000.00
2575.555TURF ESTABLISHMENTLS1$3,742.20$3,742.20$5,200.00$5,200.00$4,000.00$4,000.00$3,800.00$3,800.00
2575.571RAPID STABILIZATION METHOD 3MGAL6$200.00$1,200.00$100.00$600.00$100.00$600.00$100.00$600.00
 Totals for project Z66 $679,458.65 $689,831.25 $712,264.00 $772,438.60
 
Contract Total:$679,458.65$689,831.25$712,264.00$772,438.60