9/4/2019

CITY OF MARSHALL
Project Bid Abstract


Project Name:  SOUTH HIGH ST / SOUTH WHITNEY ST (100 & 200 BLOCK) ALLEY IMPROVEMENT PROJECT Contract No.: 
Client:  CITY OF MARSHALL Project No.:  Z70-2
Bid Opening:  09/04/2019 10:00 AM Owner:  City Of Marshall

  Project: Z70-2 - SOUTH HIGH ST / SOUTH WHITNEY ST (100 & 200 BLOCK) ALLEY IMPROVEMENT PROJECT     Engineers Estimate Towne & Country Excavating LLC A&C Excavating, LLC
Line No. Item Units Quantity Unit Price Total Price Unit Price Total Price Unit Price Total Price
1 2021.501 MOBILIZATION LS 1 $20,000.00 $20,000.00 $7,000.00 $7,000.00 $5,000.00 $5,000.00
2 2105.507 COMMON EXCAVATION (P) C Y 70 $15.00 $1,050.00 $22.00 $1,540.00 $15.00 $1,050.00
3 2105.533 SALVAGE & REINSTALL AGGREGATE BASE CU YD 70 $33.00 $2,310.00 $13.00 $910.00 $18.00 $1,260.00
4 2211.507 AGGREGATE BASE (CV) CLASS 5 MODIFIED (P) C Y 70 $40.00 $2,800.00 $24.00 $1,680.00 $30.00 $2,100.00
5 2502.503 6" PERF PVC PIPE DRAIN L F 170 $15.00 $2,550.00 $13.00 $2,210.00 $45.00 $7,650.00
6 2503.602 CONNECT TO EXISTING STORM SEWER EACH 5 $1,100.00 $5,500.00 $2,200.00 $11,000.00 $500.00 $2,500.00
7 2503.603 12" PIPE SEWER L F 245 $52.00 $12,740.00 $48.00 $11,760.00 $95.00 $23,275.00
8 2506.503 CONST DRAINAGE STRUCTURE DES 48-4020 L F 5 $550.00 $2,750.00 $1,140.00 $5,700.00 $650.00 $3,250.00
 
  Totals for Project Z70-2   $49,700.00   $41,800.00   $46,085.00
  % of Estimate for Project Z70-2       -15.90%   -7.27%
 
I hereby certify that this is an exact reproduction of bids received.


Certified By:  _______________________________  License No.  ________
Date:  ____________